Task List

Task Name Description Status Cost (UGX) Assigned to Start date
Design update and construction; Design update services. Ongoing 0 Contractor 2016-06-01
Design update and construction; General provisions including relocation of services etc. Ongoing 0 Contractor 2016-06-01
Design update and construction; Drainage including excavation, back filling, concrete works, steel works and culvert laying etc. Ongoing 0 Contractor 2016-06-01
Design update and construction; Concrete channeling. Ongoing 0 Contractor 2016-06-01
Design update and construction; Stone-pitching and Protection against erosion. Ongoing 0 Contractor 2016-06-01
Design update and construction; Earthworks. Ongoing 0 Contractor 2016-06-01
Design update and construction; Ancillary works. Ongoing 0 Contractor 2016-06-01
Design update and construction; Landscaping and grassing. Ongoing 0 Contractor 2016-06-01
Design update and construction; Drainage Structures. Ongoing 0 Contractor 2016-06-01
Design update and construction; Torrence, testing and quality control. Ongoing 0 Contractor 2016-06-01
Design update and construction; Dayworks. Ongoing 0 Contractor 2016-06-01
Leave a comment You may give feedback on the general project as a whole, or particular areas under a project, like tasks, issues, etc.
A response to your comment will be sent here within 24 hours.
Turn this on to hide your name.
Turn on to confirm this is not spam.
Project comments
Visitor comments on this project
No comments here, be the first to post a comment.